Utility | IPL/AES Indiana | NIPSCO | I&M/AEP | Duke Energy Indiana |
Cause No. & Petition | 45504 | 45505 | 45506 | 45508 |
Direct Testimony | Matthew Fields | Kevin A. Kirkham | n.a. w/i 10 days | n.a. |
Marginal DG Price | $0.02796/kWh | $0.02645/kWh | n.a. | n.a. |
Additional/Supplemental | 6/1/2021 | 05/27/2021 | ||
Pre-hearing conference | w/i 30 days | promptly | w/i 30 days | |
OUCC/Intervenors prefile | 09/09/2021 | |||
Rebuttal testimony | 09/30/2021 | |||
Evidentiary hearing | 10/25-29/2021 | |||
Target for IURC order | 07/01/2022 | 07/01/2022 | 07/01/2022 | 06/29/2022 |
Technical conference | Yes, if requested | |||
Workpapers filed | Workpaper MDF-1 |