Author Archives Laura Arnold

Kokomo (IN) Plan Commission approves solar park at former Continental Steel site

Posted by Laura Arnold  /   June 16, 2016  /   Posted in solar  /   No Comments

Development of Kokomo solar park moves forward

Plan Commission approves solar park at former Continental Steel site

The Kokomo Plan Commission approved the development plan Tuesday of a solar park at the former site of the Continental Steel plant.

The approval comes after last month’s favorable recommendation from the city plat committee for the project, which will encompass roughly 26 acres at 1201 W. Markland Ave. and include 21,000 solar panels producing seven megawatts of energy.

The solar park – originally slated for completion by the end of 2015 and expected to cost $10 million – is being developed by Inovateus Solar, a solar-integration company based in South Bend that has developed solar-energy facilities in 26 states.

With the plan commission’s approval, Inovateus Solar is expected to begin construction work immediately and likely finish this fall, according to Austin Williams, an Inovateus Solar senior account executive who provided the timeline after last month’s plat committee meeting.

Williams could not be reached Wednesday for further comment.

Tuesday’s approval comes after the Indiana Utility Regulatory Commission approved a 20-year purchased-power agreement last August between the company and Duke Energy, which will buy the electricity and distribute it on the grid.

"The usage lines up with between 500 to 1,000 [homes], but one guy could use quite a bit more than the other so it's really, really hard to tell," explained Williams about the potential impact of the park's energy distribution.

Duke Energy Indiana’s operations provide about 7,500 megawatts of owned electric capacity to approximately 810,000 customers in a 23,000-square-mile service area, making it the state’s largest electric supplier, according to a Duke press release.

In relation, Inovateus Solar and city officials are working to finalize a lease which matches the 20-year term with Duke. Williams noted the lease could eventually be extended if the panels are still producing power.

“We looked for areas where there was plenty of power draw, plenty of power load, and energy infrastructure,” he explained about the decision to build a park in Kokomo. “With Kokomo as a high industrial area, that was top of the list to start checking out.

“When we starting finding these brownfield sites it really made a lot of sense, and then the city got really excited because they’ve been vacant for a while. Kokomo is a good choice because it’s really got the population we need and the energy infrastructure,” he added later.

Formerly, the Continental Steel site was listed on the Environmental Protection Agency’s list of most dangerous sites because of the high levels of toxic pollutants in the soil.

Continental Steel went bankrupt in 1986, and studies revealed the 183-acre property was contaminated with solvents, PCBs and lead. The Indiana Department of Environmental Management and the EPA spent more than $40 million to clean up the site.

City Engineer Carey Stranahan said in a previous interview the city is on board with the new facility, which will revitalize a piece of property that has been vacant for decades.

“The reason we were interested in turning this property into a renewable energy opportunity is because we can reuse property that previously compromised the environment,” he said. “Solar energy has a very low impact on the environment, which was attractive to us.

“This also reduces maintenance by the city. We will be receiving revenue, but we will not have to invest too many resources,” he said.

George Myers can be reached at 765-454-8585, by email at george.myers@kokomotribune.com or on Twitter @gpmyerskt.


IPL Integrated Resource Plan (IRP) #2 Advisory Mtg 6/14/16; Participate remotely

Posted by Laura Arnold  /   June 14, 2016  /   Posted in Uncategorized  /   No Comments

IPL logo

Indianapolis Power & Light (IPL) Integrated Resource Plan (IRP)

Every two years Indianapolis Power & Light Company (IPL) must submit its Integrated Resource Plan (IRP) to the Indiana Utility Regulatory Commission (IURC). The plan is a 20-year forecast outlining how IPL will provide reliable electricity to its customers.

2016 IRP Public Advisory Meetings:

The second public advisory meeting for the 2016 IRP will be held Tuesday, June 14.

Meeting Materials for Public Advisory Meeting #2 include:

IRP Public Advisory Meeting #2  June 14, 2016 Agenda 

Registration & Breakfast 8:30 AM – 9:00 AM -

Welcome & Safety Message 9:00 – 9:05 AM Bill Henley, VP of Regulatory and Government Affairs

Meeting Agenda & Guidelines 9:05 – 9:10 AM Marty Rozelle, PhD, Meeting Facilitator

Summary and Feedback from IRP Public Advisory Meeting #1 9:10 – 9:25 AM Joan Soller, Director of Resource Planning

  • Stakeholder Presentation #1 9:25 – 9:40 AM Denise Abdul-Rahman, Environmental Climate Justice Chair, NAACP Indiana
  • Stakeholder Presentation #2 9:40 – 9:55 AM Dr. Stephen Jay, Professor, IU Fairbanks School of Public Health
  • Stakeholder Presentation #3 9:55 – 10:10 AM Larry Kleiman, Executive Director, Hoosier Interfaith Power & Light
  • Stakeholder Presentation #4 10:10 – 10:25 AM Jodi Perras, Senior Indiana Campaign Representative, Sierra Club Beyond Coal

BREAK 10:25 – 10:40 AM

Portfolio Comparison based on Metrics 10:40 – 11:00 AM Megan Ottesen, Regulatory Analyst

Metrics Exercise 11:00- 11:30 AM Marty Rozelle

Resource Adequacy 11:30 – 12:00 PM Ted Leffler, Senior Risk Management Analyst

LUNCH 12:00 – 12:30 PM

Transmission & Distribution 12:30 – 1:00 PM Mike Holtsclaw, Director of Engineering

Load Forecast 1:00 – 1:30 PM Eric Fox, Director of Forecast Solutions, Itron Inc.

Environmental Risks 1:30 – 2:00 PM Angelique Collier, Director of Environmental Policy

BREAK 2:00 – 2:15 PM

Modeling Update 2:15 – 2:40 PM Joan Soller

Portfolio Exercise 2:40 – 3:10 PM Marty Rozelle

Concluding Remarks & Next Steps 3:10 – 3:15 PM Marty Rozelle

Howard County (IN): Ortmans advocate renewable energy use

Posted by Laura Arnold  /   June 02, 2016  /   Posted in Uncategorized  /   No Comments

solar

Ortmans advocate renewable energy use

Cousins Randy and Stan utilize both geothermal and solar energy

Within Howard County, two cousins may make for the leading family in renewable energy.

Randy Ortman, the owner of Ortman Water and Drilling, and Stan Ortman, a local farmer and member of the Howard County Council, have both taken steps towards reducing their carbon footprint. And it’s not just for the energy savings.

“I think ... too many people worry about short term,” said Randy. “Long term for them is five or 10 years. You talk to the Japanese, and long term is 50 or 100 years or longer. I think too many people in this country, politicians in particular, think short term. If it’s less than 20 years I consider it short term. You need to be thinking long term. What can we do to conserve the resources we have for future generations and to protect those resources?”

As far as short term goes, Randy refers to the start-up costs of installing solar arrays and geothermal equipment in homes and businesses. These costs can dissuade many prospective users. However, dividends can be achieved.

In December 2014 Randy’s switch to cleaner energy for his business began with the installation of more energy efficient fluorescent lighting fixtures. In total, about 168 light bulbs in the facility were switched over to the more energy-efficient variant.

“We had an analysis done, and they thought we would save roughly 30 to 35 percent on our electrical bill just by changing light fixtures,” said Stan. “Most of these burn 40 to 50 hours a week. We’ve changed to LED, even the other incandescent bulbs. We don’t get quite the light output in those, but these LEDs, two bulbs is brighter than four fluorescents.”

By August the following year, Randy’s solar panels were installed and fully functional in September. So, for about eight months the solar array has been supplying energy to Ortman Water and Drilling. Thus far, the results are positive.

“Our electrical bill was averaging about $1,200 a month,” said Randy. “We had one month with nothing, and now it’s running between $200 and $400 a month. That’s with the LEDs and the solar.”

Cost savings with a solar array begin to take effect after a period of time. Some months see less energy produced due to cloud cover. For sunnier time periods, excess energy is gathered, and those cost savings are rolled over, making up the less productive periods. According to Randy, one of the most productive months is February because of a combination of factors. Not only is it typically sunnier then, but it’s also not as hot. Warm temperatures cause the arrays to not function at such a high level.

Randy anticipates the system will pay for itself in seven to nine years thanks in part to the 30 percent tax credit available to solar energy users. Long term, he hopes to counteract rising electric rates.

Stan’s system has been in place for a slightly longer period of time.

Production began on the solar array at his home in 2013, and he just completed his second year of creating solar energy.

 

Solar park at former Continental Steel site receives favorable recommendation

Posted by Laura Arnold  /   June 02, 2016  /   Posted in solar  /   No Comments

Inovateus Solar logo

Solar park at former Continental Steel site receives favorable recommendation

City officials made progress Wednesday on the development of a much-anticipated solar park at the former site of the Continental Steel plant, a project expected to be completed this fall.

At a Kokomo Plat Committee meeting Wednesday, a favorable recommendation for the project’s development plan approval was sent to the city plan commission, which will hear the case at 7 p.m. June 14 in City Hall.

The solar park – originally slated for completion by the end of 2015 and expected to cost $10 million – is being developed by Inovateus Solar, a solar-integration company based in South Bend which has developed solar-energy facilities in 26 states.

If the plan commission approves the project’s development plan, Inovateus Solar will begin construction work immediately and likely finish by this fall, according to Austin Williams, an Inovateus Solar senior account executive.

The park, which will be located on roughly 30 acres at 1201 W. Markland Ave., will include around 21,000 solar panels and produce seven megawatts of energy.

Wednesday’s development comes after the Indiana Utility Regulatory Commission approved a 20-year purchased-power agreement last August between the company and Duke Energy, which will buy the electricity and distribute it on the grid.

"The usage lines up with between 500 to 1,000 [homes], but one guy could use quite a bit more than the other so it's really, really hard to tell," explained Williams about the potential impact of the park's energy distribution.

Duke Energy Indiana’s operations provide about 7,500 megawatts of owned electric capacity to approximately 810,000 customers in a 23,000-square-mile service area, making it the state’s largest electric supplier, according to a Duke press release.

In relation, Inovateus Solar and city officials are working to finalize a lease which matches the 20-year term with Duke, said Williams, noting the lease could eventually be extended if the panels are still producing power.

“We looked for areas where there was plenty of power draw, plenty of power load, and energy infrastructure,” he explained about the decision to build a park in Kokomo. “With Kokomo as a high industrial area, that was top of the list to start checking out.

“When we starting finding these brownfield sites it really made a lot of sense, and then the city got really excited because they’ve been vacant for a while. Kokomo is a good choice because it’s really got the population we need and the energy infrastructure,” he added later.

Formerly, the Continental Steel site was listed on the Environmental Protection Agency’s list of most dangerous sites because of the high levels of toxic pollutants in the soil.

Continental Steel went bankrupt in 1986, and studies revealed the 183-acre property was contaminated with solvents, PCBs and led. The Indiana Department of Environmental Management and the EPA spent more than $40 million to clean up the site.

City Engineer Carey Stranahan said in a previous interview the city is on board with the new facility, which will revitalize a piece of property that has been vacant for decades.

“The reason we were interested in turning this property into a renewable energy opportunity is because we can reuse property that previously compromised the environment,” he said. “Solar energy has a very low impact on the environment, which was attractive to us.

“This also reduces maintenance by the city. We will be receiving revenue, but we will not have to invest too many resources,” he said.

In addition, Stranahan addressed Wednesday the prospect of an oft-discussed roundabout at the intersection of Markland and Park avenues.

During the meeting, Stranahan said the project will be let in December with construction expected to start next spring.

In accordance with construction, he said numerous trees from the city’s recent Park Avenue beautification project may have to be relocated.

In an effort to reduce congestion and accidents at one of Kokomo’s busiest intersections, the city and Beam, Longest & Neff agreed on March 16, 2011, to enter into a partnership for the Markland and Park avenues intersection improvement project.

George Myers can be reached at 765-454-8585, by email at george.myers@kokomotribune.com or on Twitter @gpmyerskt.

Copyright 2013 IndianaDG